New Te Ararata bridge project in Māngere.
Photo/Auckland Council
Lotu Fuli says local residents’ support helped crews deliver the Te Ararata Stream flood protection works.








A flood protection project in Auckland's Māngere has been completed on time and well within budget, Auckland councillor Lotu Fuli says.
Auckland Council expected the Te Ararata Stream flood protection project to reduce the flood risk for more than 250 properties.
Fuli said it was "extremely rare" for a council project to come in under budget and on time.
The project team credited community support with helping them complete the work in about two years, Fuli said.
She said residents stayed involved throughout the project.
"They couldn't have done it as fast as they did, were it not for the huge community support that they had."

The new Walmsley Road bridge over Te Ararata Stream in Māngere made room for the stream to be widened and naturalised. Photo/Auckland Council
Walmsley Road was fully closed between Hall Avenue and McKenzie Road for about six months while the work was underway.
“For this project, the fact we were able to get it done in two years, only two years, and well within budget, it's just amazing.”
Fuli also credited Auckland Council’s Healthy Waters team, the local board and fellow ward councillor Alf Filipaina with helping the project progress.
Auckland Council says residents and community organisations helped shape the project through a stakeholder advisory group, while mana whenua representatives were involved throughout the work as kaitiaki.

Construction at Te Ararata Stream in Māngere. Flood protection work began there and at nearby Harania Creek in 2025. Photo/Auckland Council
The council and central government co-funded the project as part of the response to the 2023 floods.
At the Budget and Performance Committee meeting on [Tuesday] 17 November, councillor Alf Filipaina said he had represented the mayor at the official opening of the Te Ararata Stream project.
He thanked fellow councillor Lotu Fuli and Houkura, Auckland’s Independent Māori Statutory Board, for advocating for the Māngere flood protection projects.
He also acknowledged the work of the local board and the council’s recovery and Healthy Waters teams.
Listen to Alf Filipaina's full interview on Pacific Mornings below:
Filipaina said the Harania Creek flood protection project in Māngere East had also officially opened.
Te Ararata and Harania were the first two flood resilience projects under the council’s Making Space for Water programme.
At Te Ararata, the council replaced the Walmsley Road bridge with a wider one, upgraded culverts at Mahunga Drive and installed a debris rack to help prevent blockages during heavy rain.
The council says more than 100 properties in the area experienced flooding at floor level during the 2023 storms.
LDR is local body journalism co-funded by RNZ and NZ On Air.